Analysis of dispatching rules in a stochastic dynamic job shop manufacturing system with sequence-dependent setup times

  • Pankaj SHARMA ,
  • Ajai JAIN
Expand
  • Department of Mechanical Engineering, National Institute of Technology, Kurukshetra 136119, India

Received date: 23 Jun 2014

Accepted date: 05 Sep 2014

Published date: 19 Dec 2014

Copyright

2014 Higher Education Press and Springer-Verlag Berlin Heidelberg

Abstract

Stochastic dynamic job shop scheduling problem with consideration of sequence-dependent setup times are among the most difficult classes of scheduling problems. This paper assesses the performance of nine dispatching rules in such shop from makespan, mean flow time, maximum flow time, mean tardiness, maximum tardiness, number of tardy jobs, total setups and mean setup time performance measures viewpoint. A discrete event simulation model of a stochastic dynamic job shop manufacturing system is developed for investigation purpose. Nine dispatching rules identified from literature are incorporated in the simulation model. The simulation experiments are conducted under due date tightness factor of 3, shop utilization percentage of 90 % and setup times less than processing times. Results indicate that shortest setup time (SIMSET) rule provides the best performance for mean flow time and number of tardy jobs measures. The job with similar setup and modified earliest due date (JMEDD) rule provides the best performance for makespan, maximum flow time, mean tardiness, maximum tardiness, total setups and mean setup time measures.

Cite this article

Pankaj SHARMA , Ajai JAIN . Analysis of dispatching rules in a stochastic dynamic job shop manufacturing system with sequence-dependent setup times[J]. Frontiers of Mechanical Engineering, 2014 , 9(4) : 380 -389 . DOI: 10.1007/s11465-014-0315-9

1
Garey M R, Johnson D S, Sethi R. The complexity of flow shop and job shop scheduling. Mathematics of Operations Research, 1976, 1(2): 117-129

DOI

2
Xiong J, Xing L N, Chen Y W. Robust scheduling for multi-objective flexible job-shop problems with random machine breakdowns. International Journal of Production Economics, 2013, 141(1): 112-126

DOI

3
Allahverdi A, Soroush H M. The significance of reducing setup time/setup costs. European Journal of Operational Research, 2008, 187(3): 978-984

DOI

4
Pinedo M. Scheduling: Theory, Algorithms and Systems. Englewood cliffs: Prentice-Hall, 1995

5
Manikas A, Chang Y L. Multi-criteria sequence-dependent job shop scheduling using genetic algorithms. Computers & Industrial Engineering, 2009, 56(1): 179-185

DOI

6
Defersha F M, Chen M Y. Jobshop lot streaming with routing flexibility, sequence-dependent setups, machine release dates and lag time. International Journal of Production Research, 2012, 50(8): 2331-2352

DOI

7
Haupt R. A survey of priority rule-based scheduling. Operations-Research-Spektrum, 1989, 11(1): 3-16

DOI

8
Ramasesh R. Dynamic job shop scheduling: A survey of simulation research. Omega, 1990, 18(1): 43-57

9
Allahverdi A, Gupta J N D, Aldowaisan T. A review of scheduling research involving setup considerations. Omega, 1999, 27(2): 219-239

DOI

10
Panwalkar S S, Iskander W. A survey of scheduling rules. Operations Research, 1977, 25(1): 45-61

DOI

11
Blackstone J H, Philips D T, Hogg G L. A state-of-the-art survey of dispatching rules for manufacturing job shop operations. International Journal of Production Research, 1982, 20(1): 27-45

DOI

12
Holthaus O, Rajendran C. New dispatching rules for scheduling in a job shop: An experimental study. International Journal of Advanced Manufacturing Technology, 1997, 13(2): 148-153

DOI

13
Jayamohan M S, Rajendran C. New dispatching rules for shop scheduling: A step forward. International Journal of Production Research, 2000, 38(3): 563-586

DOI

14
Jain A, Jain P K, Singh I P. An investigation on the performance of dispatching rules in FMS scheduling. International Journal of Simulation Modeling, 2004, 3(2-3): 49-60

15
Dominic P D D, Kaliyamoorthy S, Saravana Kumar M. Efficient dispatching rules for dynamic job shop scheduling. International Journal of Advanced Manufacturing Technology, 2004, 24(1-2): 70-75

16
Wilbrecht J K, Prescott W B. The influence of setup time on job shop performance. Management Science, 1969, 16(4): 274-280

DOI

17
Kim S C, Bobrowski P M. Impact of sequence dependent setup time on job shop scheduling performance. International Journal of Production Research, 1994, 32(7): 1503-1520

DOI

18
Kim S C, Bobrowski P M. Scheduling jobs with uncertain setup times and sequence dependency. Omega, 1997, 25(4): 437-447

19
Vinod V, Sridharan R. Dynamic job shop scheduling with sequence-dependent setup times: Simulation modelling and analysis. International Journal of Advanced Manufacturing Technology, 2008, 36(3-4): 355-372

DOI

20
Baker C T, Dzielinski B P. Simulation of a simplified job shop. Management Science, 1960, 6(3): 311-323

DOI

21
Yu X, Ram B. Bio-inspired Scheduling for dynamic job shops with flexible routing and sequence dependent setups. International Journal of Production Research, 2006, 44(22): 4793-4813

DOI

22
Rossi A, Dini G. Flexible job shop scheduling with routing flexibility and separable setup times using ant colony optimisation method. Robotics and Computer-integrated Manufacturing, 2007, 23(5): 503-516

DOI

23
Baykasoğlu A, Göçken M, Unutmaz Z D. New approaches to due date assignment in job shops. European Journal of Operational Research, 2008, 187(1): 31-45

DOI

24
Rangsaritratsamee R, Ferrell W G Jr, Kurz M B. Dynamic rescheduling that simultaneously considers efficiency and stability. Computers & Industrial Engineering, 2004, 46(1): 1-15

DOI

25
Van Parunak H. Characterizing the manufacturing scheduling problem. Journal of Manufacturing Systems, 1991, 10(3): 241-259

DOI

26
Baker K R. Sequencing rules and due-date assignments in a job shop. Management Science, 1984, 30(9): 1093-1104

DOI

27
Law A M, Kelton W D. Simulation Modeling and Analysis. New York: McGraw-Hill, 1991

Outlines

/