Jun 2024, Volume 11 Issue 1
    

  • Select all
  • You Qingzhong
    2009, 11(1): 2-5.
    The paper analyzes existing state of innovation system in the field of public infrastructure construction in China and elaborates on the duty and role of owner in establishment of a technical innovation system with enterprise as the main body following the process of productioneducationresearch. This paper also claims that the key project construction is an important resource to enhance national capability of innovation and accordingly puts forward an effective approach to cultivate the core competitiveness of leading enterprises on the basis of practice in the Sutong Bridge project.
  • He Huawu
    2009, 11(1): 4-16.

    High speed railway is a complicated and enormous system. Beijing-Tianjin inter-city railway is the first high speed railway that has started commercial operation in China. There are significant innovations made on key technologies and four challenging issues including system design and integration, high track regularity and stability, high safety and riding comfort, reliable operational control and high efficiency. China Railways experienced three years to build Beijing-Tianjin inter-city railway. The operational performances of Beijing-Tianjin inter-city railway showed that the whole technology is ranking at the leading position in the world. The technologies are convincing exemplary demonstration and will be applied to build the high speed railway network in the future.

  • Zhang Xigang1, Yuan Hong1, Pei Minshan1, Dai Jie2, Xu Lin1
    2009, 11(1): 6-11.
    The main span of Sutong Bridge is a doublepylon, doubleplane cablestayed bridge with steel box girder, which has the world’s longest central span of 1 088 m within cablestayed bridges. To overcome problems caused by severe meteorological conditions, perplexing hydrological conditions, deep buried bedrock and higher navigation level, many new technics and methods were created. Keys including structural system, steel box girder, stayed cable, tower, pier, tower foundation, collision avoidance system, windresistance, seismicresistance, structural nonlinear response and structural static stability were presented individually in this paper.
  • Zhang Xigang1, Pei Minshan1, Yuan Hong1, Xu Liping2, Zhu Bin1
    2009, 11(1): 12-17.
    Sutong Bridge, whose layout is [(100+100+300) +1 088 + (300+100+100)] m,marks the largest span of cablestayed bridges in the world. The complex natural condition at the bridge site and the strict requirements for resistance of wind and seismic action make it crucial to choose a favorable structural system to assure the function and safety of the bridge. The comparison among several optional structural systems for Sutong Bridge is illustrated. After detailed analysis is carried out for viscous damper and hydraulic buffer, super liquid viscous damper with additional displacement limitation is designed for the first application in bridge engineering. The parameters for the damper is analyzed and studied and the dampers are installed successfully after quality tests.
  • Gao Zongyu
    2009, 11(1): 17-21.

    The steel truss structure is adopted for all of these bridges of the under construction Beijng-Shanghai and Beijing-Guangzhou High Speed Railways across Yangtze River and Yellow River, and they are multy railway lines or rail-cum-road bridges, with heavy loading capacity and high railway operation speeds. Some new materials, new structures and new workmanship are applied accordingly.

  • Pei Minshan, Zhang Xigang, Zhu Bin, Hou Bin, Liu Changpeng
    2009, 11(1): 18-22.
    Along with the expanding of span of cablestayed bridge, wind load becomes a more and more important controlling factor for bridge the design. A very large proportion of the wind load acting on cables has exceeded that acting on deck. There was not any detailed prescript in Chinese code for calculation of longitudinal wind load on cables due to lack of theoretical research and experiment, and conservative simplified calculation was adopted during design, which leads to conservative and uneconomical design of structures. To resolve this problem, cable force experiment was carried out during the design of Sutong Bridge. By comparing with international research results, the calculation formula of longitudinal wind drag coefficient for cables was advanced to fill the blank of bridge wind resistant code of China, and has already been adopted in the Highway Bridge Wind Resistant Design Code (JTG/T D60012004) with great significance for bridge engineering.
  • Du Jiajun
    2009, 11(1): 22-25.

    According to the features of bridges in the section between Beijing and Cangzhou in Beijing-Shanghai high-speed railway, the construction and technical innovations which include special representative structure of bridges, control measures on settlement after the completion of bridges in the regional land subsidence area and assurance methods on high track regularity of ballastless track in 350 km/h speed are mainly introduced.

  • Ye Aijun1, Wu Shouchang2
    2009, 11(1): 23-29.
    Based on the capacity/demand (C/D) analysis of bridge components, and life cycle and performance based seismic design principles, a practical approach is developed for the seismic performance evaluation of superlong span cablestayed bridges. According to the approach, the seismic performance evaluation of the Sutong Bridge,which is a cablestayed bridge with a main span of 1 088 m, is completed, and the practicality of the approach is validated. The earthquake resistance level for superlong span cablestayed bridges is discussed, including the earthquake level, its corresponding structural performance and check indices. And a set of formula for capacity/demand ratio calculation of bridge components is proposed.
  • Gao Zhishuang, Zhao Nianquan, Zhao Changyu, Hu Mingwen, Gou Yunlong
    2009, 11(1): 26-31.

    Based on engineering practice in Beijing-Shanghai high speed railway, effect to concrete workability, meachincal performance, and durability of mineral admixtures are studied, at the same time the preparing technology of high performance concrete with high-volume supplemementary cementitious materials are studied. Combining with pracitce engineering, control technology of raw materials, design of mixing proporation and construction for high performance concrete with high-volume supplemementary cementitious materials are introduced.

  • Ren Huixing, Ouyang Xiaoyong, He Maosheng, Nie Qinlong, Wang Xiali
    2009, 11(1): 30-36.
    This paper, from three aspects including construction conditions, foundation design and construction, introduces some considerations in the designing of mainpylon foundations and some practical measures to deal with certain unfavorable construction conditions, such as deep water, tidal effect, soft stratum and heavy traffic, during the construction of mainpylon foundations.
  • Sun Shuli,Zhang Wenjian,Wang Zhaohu,Su Wei,Wu Cailan,Bu Qinghao
    2009, 11(1): 32-42.

    Beijing-Tianjin inter-city railway is the first built passenger dedicated line with the speed of 350 km/h in our country. During the design, new ideas of bridge construction were carried out in order to ensure the safety, amenity and stability requirements of the train under high-speed condition. At the same time, concepts of environmental adaptability, serving for transportation and comprehensive benefits were followed. In the whole line of the railway, long-bridge scheme was adopted, and the most advanced technology of unballasted track was utilized in bridges which account for 87.7 % of the total line. The success of the design and construction of bridges in Beijing-Tianjin inter-city railway accumulated valuable experiences for large-scale construction of high-speed railway at the future. And roles of demonstration, landmark and prototype are played at the same time.

  • He Ping,Guan Yijun,Zhang Xiongwen,Zhang Qun,Zhou Jianhua
    2009, 11(1): 37-44.
    Sutong Bridge, as a worldrecord cablestayed bridge with its main span exceeding 1 000 m constructed in Yangtze River estuary region in China, is located at a site with complicated hydrologic conditions and poor geotechnical conditions and therefore, scour protection will be a decisive factor for ensuring smooth and successful construction of this bridge. This paper, starting from structural description of deepwater group pile foundation, analyzes impact to the bridge safety introduced by scour and its protection and further presents different solutions of scour protection for foundation structures of this bridge.
  • Ding Yuanwen
    2009, 11(1): 43-47.

    Specific requirements and methods of settlement monitoring which are used in bridge of unballasted track passenger dedicated line or high-speed railway are introduced systematically, and mathematical model and determinant conditions of settlement are proposed simultaneously, taking Beijing-Tianjin inter-city railway as an example.

  • Luo Chengbin1, Zhou Jianlin2 ,Tian Wei3, Dai Jie4
    2009, 11(1): 45-51.
    Sutong Bridge tower which is 300.4 m is the highest one in the world. The tower anchor area uses the steelconcrete composite structure, its structure and the stress mechanism are complex, so it must be paid more attention to the structure durable issue. The 300 m height makes the tower quite sensitive to the environmental factors such as wind and temperature. The wind resistance safety of tower in construction stage is especially important. In this paper, the design of composite structure is introduced. The key technologies of tower geometry control and wind resistance in construction stage are analyzed.
  • Li Mingling
    2009, 11(1): 48-59.

    The criterion for residual deformation of Substructure of unballasted track on railway passenger dedicated line is extremely strict in order to satisfy the safety and comfort requirements of the high-speed train. Based on new Wuhan(Guangzhou railway passenger dedicated line engineering practice,this paper introuduces the key technologies for the deformation monitoring, data management and analysis system, the prediction method and assessment criterion are put forward to determine the reasonable time of unballasted track laying to guarantee the quality of unballasted track. Some advice provide reference for the ongoing unballasted track on railway passenger dedicated line construction.

  • Ding Feng1, Sang Chunming2, Zhou Daiyi2, Bai Bingdong1
    2009, 11(1): 52-58.
    This paper focuses on introducing the manufacture technology of 1 770 MPa galvanized steel wires for stay cables applied to domestic bridges. During the development practices of high strength galvanized wire for stay cables used in Sutong Bridge, Baosteel has established three key technologies based on research of manufacture technology and technical innovation. The three key technologies are: “Double Tensioning + limiter die” process, “dominant process + fine adjustment” in integrated optimization technology and “threelevel control” in hot dip galvanization. With these key technologies, Baosteel has produced 1 770 MPa galvanized wires for stay cable, which has high tensile strength, low relaxation and good torsion performances.
  • Rao Huarong, Deng Huibin
    2009, 11(1): 59-62.
    In the background of the construction of Sutong Yangtze River Bridge (short as Sutong Bridge), the cable construction method and techniques of a thousandmeter scale cablestayed bridge are introduced. Some key construction techniques, such as outspreading cable on deck, installing cable at pylon, pulling and fixing cable at the attachment with decks and cable PE sheath protection are discussed.
  • Song Jinxi
    2009, 11(1): 60-66.

    As a case for study, the online montoring and numerical analysis for 32 m concrete prestressed box girder prestressing and elastic camber effect in Wuhan-Guangzhou passenger express line was performed in the paper. The effect of monitoring and analysis, based on the engineering practice, the control measures of the box girder creep camber were put forward, which can be taken as a reference and experience guidance for the similar projects.

  • Chen Ming1, Wu Qihe2, Luo Chengbin1, Zhou Hanfa2
    2009, 11(1): 63-68.
    Sutong Bridge is a cablestayed bridge with a steel box girder and a main span of 1 088 m. The steel box girder of main span includes five portions: back span large unit, large block of pylon, standard girder, back span closure girder and middle span closure girder. Each back span large unit is fabricated by welding several deck segments together in factory, and is erected by floating crane. As navigational clearance of the main bridge is high, the traditional truss lifting device can’t satisfy the requirement of domestic lifting cranes for this kind of lifting height and weight. Hence, a kind of lighter lifting device for the erection of back span large units was accepted for this bridge. In this paper, the design and use of this lifting device is introduced.The upper structure used lifting gantry to install the standard girder segment by cantilever method. Because the bridge’s navigation clearance is high, and the girder segment is wide and heavy, the meteorology and hydrology condition of the bridge district is abominable, and the requirements of long cable girder side pullin, structure and performance propose high request to the lifting gantry. In this paper, the design and use key point of long cable pullin angle adjustment device integrate into lifting gantry is introduced.
  • Wang Zhibin,Wang Qingming
    2009, 11(1): 67-74.

    On the basis of the research results of the project, the Research on the Industrialization of Freely Supported Box and Girder for Passenger Express Line, in Ministry of Railways and China Railway Construction Corporation, and the programming and design experience for almost 30 girder prefabrication fields, the three important aspects of girder field construction, i.e. site election, plane layout and corollary equipment, are discussed in depth.

  • Chen Ming1, Luo Chengbin1, Wu Qihe1,2, Zhang Yongtao1,2, You Xinpeng1,2
    2009, 11(1): 69-75.
    Sutong Bridge is a cablestayed steel box girder bridge with a main span of 1 088 m. The erection of upper structure adopts geometry control method and requires no change to the unit’s size and the structure’s nonestress geometry. Before main span closure, the cantilever of girder reaches 540.8 m, the structure state is noticeably influenced by external circumstances, the main span closure face great difficulty. By abstracting the advantage of the pullback method abroad and the domestic temperaturecutting method, a new assistant pullback method have put forward and bring into practice actually. In this paper, the analysis key point of practice conditions, key parameter of practice, main measures of the method and the performance is introduced.
  • Huang Zhijiu
    2009, 11(1): 75-80.

    Polycarboxylates water-reducing admixture possesses the capability which could meat with the comprehensive performance of high performance concrete using in field of passenger dedicated line. Problems of engineering application of polycarboxylates water-reducing admixtures were analyzed. At present the key for polycarboxylates application is to settle the compatibility with cement andkeep the quality retention of this admixtures.

  • Zhang Hong1, Luo Chenbin2, Zhang Yongtao2, You Xinpeng2
    2009, 11(1): 76-82.
    The Sutong Yangtze River Bridge (short as Sutong Bridge) is now the largest span cablestayed bridge in the world. The construction of the superstructure of the middle bridge covered several stages including erection of the big block girders for the side span, assistant span and tower area, erection of standard girders and closure of the middle span. The big block girders were hoisted by a floating crane, and the standard girders were hoisted by a double crane system on the deck. The pushing assistant method was adopted for the middle span closure construction. Furthermore, key technologies and innovative methods used in the processes of girder erection and cable assemblage in all stages were expatiated systematically. An allstage self adaptive geometry control method was used in the construction process. By accurately controlling the unstressed dimensions and shape of all structural components in each step, and realization that the control system and the controlled system adapt to each other, the goal was to make control of the final line shape and inner force of the bridge structure achievable. Two solutions, including GPS based and total station based dynamic geometry monitoring systems, were used to resolve the measure problem under the wide–range of windinduced vibrations in the long cantilever state. Finally, research on the windinduced vibration of the superstructure during the construction period was executed. Buffeting response analysis to the longest single and double cantilever states were carried out. The analysis and evaluation of wind resistance safety of the main girders under the longest single cantilever state was made, and corresponding wind resistance measures were suggested. The asbuilt geometric error and cable force error were controlled in a required design range, and this whole technological achievement can be a benchmark for construction of other large span cablestayed bridges in the future.
  • Li Chenggen and Gao Ri
    2009, 11(1): 81-86.
    Based on the idea of bearing function separation, a structural member called shock absorber that makes use of its plastic deformation, is presented for reducing the seismic response of the bridge. The design criterion, for matching material stress, strain and earthquake fortification aim, is also given. The analysis results show that the high speed railway box girder with the absorber in this paper has great reduction of seismic response of the bridge piers.
  • Fang Jianhua1,Xu Yanmin2, Liu Mingjun2, Zhang Jingcheng2, Li Bing2
    2009, 11(1): 83-86.
    Motion state of ship out of control in bridge area was analyzed. Motion procedure after losing control was divided into two steps. One is drift step within stopping period. The other is drift step without inertia, which is induced by wind and current. Mathematical model for motion of ship out of control, considering wind-induced drift, current-induced drift, stopping ability, etc., was established. Dangerous collision areas for main pier and auxiliary piers were analyzed according to different calculation conditions.
  • Huang Can, Bu Yizhi, Zhang Qinghua
    2009, 11(1): 87-91.

    Take Sutong Bridge as the subject investigated, the correctness of the geometry control theory is verified by the numerical simulation analysis. The influences of structural geometric shape induced by temporary loads and temperature field during the construction procedure are investigated. Taking the impact of geometry non-linear during construction into account, the simulation results indicate that only the stage state of the structure during construction is affected and the completion stage state is not affected. Geometry control theory applied to control the super-span cable-stayed bridge construction, and satisfied outcome of construction control can be achieved based on geometry control theory.

  • Yan Ping
    2009, 11(1): 92-96.

    Urban rail transit construction in our country is now stepping into a quickly developing period. Based upon urban rail transit planning of Beijing, this article analyzes questions existing in urban rail transit planning, construction and management. Using international metropolis's urban rail transit planning, construction and management experience for reference, the article brings forward optimized countermeasures on building synthesized harmonizing mechanism, perfecting urban rail transit planning and creating synthesized communication hinges, as well as giving concrete suggestions on urban rail transit's transfer and joint by utilizing state railway resources.

  • Fa Yueping1, Li Zhen2
    2009, 11(1): 93-101.
    Objectives define the boundaries of complex engineering system. It is a hard work to identify the specific objectives of a complex engineering system. The objectives system development needs a complicated process, from nix to prototype, and to final definition. The total process will cover the following course: from chaos to wellordered; from qualitativeness to combination of quantitativeness and qualitativenss, then from qualitativeness to quantitativeness (a recurrent process), expert experience and theoretical science, rationality and sensibility, synthesis analysis and metasynthesis, routinization and nonroutinization. Such process is explicit in phase development yet overlapped; mutually confined yet mutually independent; permeated conflicts yet pregnant in harmony. This article explores the complexity of Sutong Bridge’s objectives development and the process of metasynthesis in the Sutong Bridge engineering.