Analysis and design of trial well mooring in deepwater of the South China Sea

Yongfeng Guo , Shaojun Ji , Changquan Tang , Jiansong Li , Huiquan Zhong , Ong Chin Yam Ian

Journal of Marine Science and Application ›› 2012, Vol. 11 ›› Issue (2) : 222 -227.

PDF
Journal of Marine Science and Application ›› 2012, Vol. 11 ›› Issue (2) : 222 -227. DOI: 10.1007/s11804-012-1126-1
Article

Analysis and design of trial well mooring in deepwater of the South China Sea

Author information +
History +
PDF

Abstract

Mooring systems play an important role for semi-submersible rigs that drill in deepwater. A detailed analysis was carried out on the mooring of a semi-submersible rig that conducted a trial well drilling at a deepwater location in the South China Sea in 2009. The rig was 30 years old and had a shallow platform with a designed maximum operating water depth of 457 m. Following the mooring analysis, a mooring design was given that requires upgrading of the rig’s original mooring system. The upgrade included several innovations, such as installing eight larger anchors, i.e. replacing the original anchors and inserting an additional 600 m of steel wires with the existing chains. All this was done to enhance the mooring capability of the rig in order for the rig to be held in position to conduct drilling at a water depth of 476 m. The overall duration of the drilling was 50 days and the upgraded mooring system proved to be efficient in achieving the goal of keeping the rig stationary while it was drilling the trial well in the South China Sea. This successful campaign demonstrates that an older semi-submersible rig can take on drilling in deep water after careful design and proper upgrading and modification to the original mooring system.

Keywords

offshore / anchor operation / mooring / chain / wire / chaser / drilling engineering / semi submersible / South China Sea / anchor handling vessel (AHV)

Cite this article

Download citation ▾
Yongfeng Guo, Shaojun Ji, Changquan Tang, Jiansong Li, Huiquan Zhong, Ong Chin Yam Ian. Analysis and design of trial well mooring in deepwater of the South China Sea. Journal of Marine Science and Application, 2012, 11(2): 222-227 DOI:10.1007/s11804-012-1126-1

登录浏览全文

4963

注册一个新账户 忘记密码

References

[1]

API RP 2SK (2005), Design and Analysis of Station keeping Systems for Floating Structures-Third Edition

[2]

Della R.P (1987). System development and use to position mooring system and semi submersible platform in 2,910 ft of water. OTC (Offshore Technology Conference), 5607-MS, Houston, USA

[3]

Breese G (1988). Deepwater moorings for the Green Canyon Block 29 development. OTC (Offshore Technology Conference), 5844-MS, Houston, USA

[4]

Frank Lim (2007). The report on China offshore trial string analysis for China Oilfield Services Limited. No. 5002-RPT-0008, London

[5]

Guo Y., Ji S., Tang C. Development of ASDD deepwater drilling device and its test. Oilfield Equipment, 2010, 39(2): 29-22

[6]

Guo Y., Ji S., Tang C. New device for drilling in deepwater under semi submersible: ABS unit, 2006, Bangkok, Thailand: SPE (Society of Petroleum Engineers) 101349

[7]

Guo Y., Ji S., Tang C. Development the artificial seabed technology and implementation pretrial well in the South China Sea. Journal of Marine Science Application, 2009, 8: 246-251

[8]

Metocean Criteria (2007), South China Sea Block 42/05-Ocean Weather.

[9]

ISO 19901-7 Petroleum and natural gas industries-specific requirements for floating offshore structures (2005), Part 7: Station keeping for floating offshore structures and mobile offshore units — 1st ed. 2005-12-01.

AI Summary AI Mindmap
PDF

144

Accesses

0

Citation

Detail

Sections
Recommended

AI思维导图

/