Analysis and design of trial well mooring in deepwater of the South China Sea
Yongfeng Guo , Shaojun Ji , Changquan Tang , Jiansong Li , Huiquan Zhong , Ong Chin Yam Ian
Journal of Marine Science and Application ›› 2012, Vol. 11 ›› Issue (2) : 222 -227.
Analysis and design of trial well mooring in deepwater of the South China Sea
Mooring systems play an important role for semi-submersible rigs that drill in deepwater. A detailed analysis was carried out on the mooring of a semi-submersible rig that conducted a trial well drilling at a deepwater location in the South China Sea in 2009. The rig was 30 years old and had a shallow platform with a designed maximum operating water depth of 457 m. Following the mooring analysis, a mooring design was given that requires upgrading of the rig’s original mooring system. The upgrade included several innovations, such as installing eight larger anchors, i.e. replacing the original anchors and inserting an additional 600 m of steel wires with the existing chains. All this was done to enhance the mooring capability of the rig in order for the rig to be held in position to conduct drilling at a water depth of 476 m. The overall duration of the drilling was 50 days and the upgraded mooring system proved to be efficient in achieving the goal of keeping the rig stationary while it was drilling the trial well in the South China Sea. This successful campaign demonstrates that an older semi-submersible rig can take on drilling in deep water after careful design and proper upgrading and modification to the original mooring system.
offshore / anchor operation / mooring / chain / wire / chaser / drilling engineering / semi submersible / South China Sea / anchor handling vessel (AHV)
| [1] |
API RP 2SK (2005), Design and Analysis of Station keeping Systems for Floating Structures-Third Edition |
| [2] |
Della R.P (1987). System development and use to position mooring system and semi submersible platform in 2,910 ft of water. OTC (Offshore Technology Conference), 5607-MS, Houston, USA |
| [3] |
Breese G (1988). Deepwater moorings for the Green Canyon Block 29 development. OTC (Offshore Technology Conference), 5844-MS, Houston, USA |
| [4] |
Frank Lim (2007). The report on China offshore trial string analysis for China Oilfield Services Limited. No. 5002-RPT-0008, London |
| [5] |
|
| [6] |
|
| [7] |
|
| [8] |
Metocean Criteria (2007), South China Sea Block 42/05-Ocean Weather. |
| [9] |
ISO 19901-7 Petroleum and natural gas industries-specific requirements for floating offshore structures (2005), Part 7: Station keeping for floating offshore structures and mobile offshore units — 1st ed. 2005-12-01. |
/
| 〈 |
|
〉 |