Design and implementation of model test installation of heave compensation system of deepsea mining

Qiong Hu , Shao-jun Liu , Hao Zheng

Journal of Central South University ›› 2011, Vol. 18 ›› Issue (3) : 642 -649.

PDF
Journal of Central South University ›› 2011, Vol. 18 ›› Issue (3) : 642 -649. DOI: 10.1007/s11771-011-0742-2
Article

Design and implementation of model test installation of heave compensation system of deepsea mining

Author information +
History +
PDF

Abstract

In order to validate the simulation model and develop heave compensation control strategy, heave compensation model tests were performed. The model test installation includes the mining ship motion simulator, the heave compensation system, the lifting pipe simulator, the buffer simulator and the water pool. The tests of mining ship motion simulator show that it is able to perform under the predetermined attitude path smoothly and can meet the requirements of the mining ship motions. The heave compensation effect is more than 60% under random wave and the goal is set to be 50%. The model test results indicate that this heave compensation system is effective and feasible.

Keywords

deepsea mining / heave compensation / model test installation / mining ship / motion simulator / gimbal

Cite this article

Download citation ▾
Qiong Hu, Shao-jun Liu, Hao Zheng. Design and implementation of model test installation of heave compensation system of deepsea mining. Journal of Central South University, 2011, 18(3): 642-649 DOI:10.1007/s11771-011-0742-2

登录浏览全文

4963

注册一个新账户 忘记密码

References

[1]

LiuS.-j., WangG., LiLi.. Virtual reality research of ocean poly-metallic nodule mining based on COMRA mining system [C]. Proceedings of 5th ISOPE Ocean Mining Symposium, 2003, Tsukuba, International Society of Offshore and Polar Engineers: 104-111

[2]

ChungJ. S.. Deep-ocean mining technology: Development II [C]. Proceedings of 6th ISOPE Ocean Mining Symposium (OMS-2005), 2005, Changsha, International Society of Offshore and Polar Engineers: 1-6

[3]

ChungJ. S.. The Hughes Glomar Explorer and a 5,000-m-long heavy-hift pipe: Coupled ship and pipe motions measured in North Pacific ocean [C]. Proceedings of 19th International Society of Offshore and Polar Engineers Conference, 2009, Osaka, International Society of Offshore and Polar Engineers: 330-335

[4]

FengY.-l., LiH.-r., ZhangY.-xian.. Axial oscillation of a 5 000 m lifting pipe [J]. Metal Mine, 1999, 51(4): 11-18

[5]

FangH.-can.Theoretical basis of offshore oil drilling equipment [M], 1984, Beijing, Petroleum Industry Press: 285

[6]

STEVESON W D. Heave compensation device for marine use: US 3946559 [P]. 1976-03-30.

[7]

McNARYJ. F., PersonA., OzudogruY. H.. A 7 500-ton-capacity, shipboard, completely gimbaled and heave-compensated platform [J]. Journal of Petroleum Technology, 1977, 29(4): 439-448

[8]

BLANCHET J. Ocean floor dredge system having a pneumohydraulic means suitable for providing tripping and heave compensation modes: US 4382361 [P]. 1983-05-10.

[9]

LANG D, ERIC P. Heave compensation for a pipeline hoisting system: US, WO 85/01775 [P]. 1985-04-25.

[10]

KordeU. A., DriveA.. Active heave compensation on drill-ships in irregular waves [J]. Ocean Engineering, 1998, 25(7): 541-561

[11]

KNUTESN H, ANDRESEN J. Heave compensation system: US, WO071862 A1 [P]. 2004-02-17.

[12]

YoonC. H., ParkY. C., ParkJ. M., KimY. J., KangJ. S., KwonS. K.. Solid-liquid flow experiment with real and artificial manganese nodules in flexible hoses [J]. International Journal of Offshore and Polar Engineering, 2009, 19(1): 77-79

[13]

DeepakC. R., RamjiS., RameshN. R.. Development and testing of underwater mining systems for long term operations using flexible riser [C]. Proceedings of 8th ISOPE Ocean Mining Symposium (OMS-2007), 2007, Prague, International Society of Offshore and Polar Engineers: 166-170

[14]

YangN., TangD.-s., YangLing.. The lifting installation of manganese nodules and pump test [C]. Proceedings of 8th ISOPE Pacific/Asia Offshore Mechanics Symposium, 2008, Bangkok, International Society of Offshore and Polar Engineers: 30-35

[15]

XIAO Ti-bing, WU Bai-hai. Design and experimental study of heave compensation simulating test system [J]. Machine Tool & Hydraulics, 2003(4): 36–39. (in Chinese)

[16]

XIAO Ti-bing, WU Bai-hai, LUO Zhong-hui. Research on design and simulation of active heave compensation system of heavy lifting mine pipeline [J]. Machine Tool & Hydraulics, 2002(6): 47–51. (in Chinese)

[17]

ChungJ. S.. Motion and positioning control of deep-ocean ship-riser-equipment system: Deep-ocean test experiences for doing deeper [C]. Proceedings of 3rd International Deep-Ocean Technology Symposium, 2009, Beijing, International Society of Offshore and Polar Engineers: 90-97

[18]

HuQ., LiuS.-jun.. Research on physical simulation test installation of heave compensation system of deepsea mining [C]. Proceedings of 8th ISOPE Ocean Mining Symposium (OMS-2009), 2009, Chennai, International Society of Offshore and Polar Engineers: 204-207

[19]

HuQ., ZhengH., LiuS.-j., YangNing.. A hardware-in-the-loop simulation system of heave compensation of deepsea mining [C]. Proceedings of 8th ISOPE Ocean Mining Symposium (OMS-2009), 2009, Chennai, International Society of Offshore and Polar Engineers: 197-203

AI Summary AI Mindmap
PDF

143

Accesses

0

Citation

Detail

Sections
Recommended

AI思维导图

/