Digital twin-enabled simulation system for NATM tunnel construction process considering multi-source uncertainty

Sicheng Zhao , Yi Shen , Mei Yin , Tao Li , Wei Wu , Xiaojun Li

Underground Space ›› 2026, Vol. 28 ›› Issue (3) : 278 -306.

PDF (9479KB)
Underground Space ›› 2026, Vol. 28 ›› Issue (3) :278 -306. DOI: 10.1016/j.undsp.2025.05.012
Research Paper
research-article
Digital twin-enabled simulation system for NATM tunnel construction process considering multi-source uncertainty
Author information +
History +
PDF (9479KB)

Abstract

During the construction of new Austrian tunnelling method (NATM) tunnels, inherent multi-source uncertainties may lead to substantial economic losses and project delays. To address this issue, a simulation system enabled by digital twin (DT) technology was developed. Guided by the concept of five-dimensional DT, a four-layer system architecture was established, including perception, transmission, modelling, and alternation layers. An integrated discrete event simulation (DES) model was then developed as the core of the system using structured system analysis. The model accounts for both geological and construction-related uncertainties, including routine delays and accident recovery durations. Geological uncertainties are represented through a stochastic geological modelling approach based on the Markov random field (MRF). Construction-related uncertainties are addressed using a tunnel vulnerability evaluation method based on the analytic hierarchy process – decision-making trial and evaluation laboratory (AHP–DEMATEL) method, along with the fitting of delay probability density functions. Finally, the proposed system was validated and evaluated in a real-world tunnel project. The results demonstrate that the system effectively analyzes multiple uncertainties, accurately estimates the construction schedule, enhances communication with the construction site, and ensures the safe and efficient completion of the project.

Keywords

NATM tunnelling / Digital twin / Process simulation / Markov random field / Tunnelling uncertainty

Cite this article

Download citation ▾
Sicheng Zhao, Yi Shen, Mei Yin, Tao Li, Wei Wu, Xiaojun Li. Digital twin-enabled simulation system for NATM tunnel construction process considering multi-source uncertainty. Underground Space, 2026, 28 (3) : 278-306 DOI:10.1016/j.undsp.2025.05.012

登录浏览全文

4963

注册一个新账户 忘记密码

References

[1]

Abdelmegid, M. A., González, V. A., O’Sullivan, M., Walker, C. G., Poshdar, M., & Ying, F. (2020). The roles of conceptual modelling in improving construction simulation studies: A comprehensive review. Advanced Engineering Informatics, 46, 101175.

[2]

AbouRizk, S . (2010). Role of simulation in construction engineering and management. Journal of Construction Engineering and Management, 136(10), 1140-1153.

[3]

Al-Bataineh, M., AbouRizk, S., & Parkis, H. (2013). Using simulation to plan tunnel construction. Journal of Construction Engineering and Management, 139(5), 564-571.

[4]

Al-Harbi, K. M. A. (2001). Application of the AHP in project management. International Journal of Project Management, 19(1), 19-27.

[5]

Bi, L., Ren, B. Y., Zhong, D. H., & Hu, L. X. (2015). Real-time construction schedule analysis of long-distance diversion tunnels based on lithological predictions using a Markov process. Journal of Construction Engineering and Management, 141(2), 04014076.

[6]

Bian, X., Fan, Z. Y., Liu, J. X., Li, X. Z., & Zhao, P. (2024). Regional 3D geological modeling along metro lines based on stacking ensemble model. Underground Space, 18, 65-82.

[7]

Borshchev, A. (2014). Multi-method modelling: AnyLogic. In Discrete-event simulation and system dynamics for management decision making (pp. 248-279). John Wiley & Sons Inc.

[8]

Brewer, J . (1978). Kronecker products and matrix calculus in system theory. IEEE Transactions on Circuits and Systems, 25(9), 772-781.

[9]

Cho, S. E. (2007). Effects of spatial variability of soil properties on slope stability. Engineering Geology, 92(3/4), 97-109.

[10]

Clifford, P. (1990). Markov random fields in statistics. In Disorder in physical systems: A volume in honour of John M. Hammersley on the occasion of his 70th birthday (pp. 19-32). Clarendon Press.

[11]

Dang, T. T., Schoesser, B., Thewes, M., & Koenig, M. (2018). Evaluation of productivities influenced by disturbances and different soil compositions in microtunnelling using process simulation. Tunnelling and Underground Space Technology, 76, 10-20.

[12]

Elfeki, A., & Dekking, M. (2001). A Markov chain model for subsurface characterization: Theory and applications. Mathematical Geology, 33, 569-589.

[13]

Es-haghi, M. S., Anitescu, C., & Rabczuk, T. (2024). Methods for enabling real-time analysis in digital twins: A literature review. Computers & Structures, 297, 107342.

[14]

Fang, W. L., Chen, W. Y., Love, P. E. D., Luo, H. B., Zhu, H. M., & Liu, J. J. (2024). A status digital twin approach for physically monitoring over-and-under excavation in large tunnels. Advanced Engineering Informatics, 62, 102648.

[15]

Fenton, G. A., & Griffiths, D. V. (2008). Risk assessment in geotechnical engineering. John Wiley & Sons Inc.

[16]

Friedenthal, S., Moore, A., & Steiner, R. (2014). A practical guide to SysML: The systems modeling language. Morgan Kaufmann.

[17]

Frough, O., Khetwal, A., & Rostami, J. (2019). Predicting TBM utilization factor using discrete event simulation models. Tunnelling and Underground Space Technology, 87, 91-99.

[18]

Haas, C., & Einstein, H. H. (2002). Updating the decision aids for tunnelling. Journal of Construction Engineering and Management, 128(1), 40-48.

[19]

Hao, L., Wan, F. C., Ma, N., & Wang, Y. C. (2018). Analysis of the development of WeChat mini program. Journal of Physics: Conference Series, 1087(6), 062040.

[20]

Khetwal, A., Rostami, J., Frough, O ., & Nelson, P. P. (2021a). Comparison between discrete event simulation approach and various existing empirically-based models for estimation of TBM utilization. Tunnelling and Underground Space Technology, 112, 103883.

[21]

Khetwal, A., Rostami, J., & Nelson, P. P. (2022). Introducing uniform discrete event simulation (CSM2020) for modeling the TBM tunnelling process. Tunnelling and Underground Space Technology, 125, 104502.

[22]

Khetwal, S. S., Pei, S. L., & Gutierrez, M. (2021b). Stochastic event simulation model for quantitative prediction of road tunnel downtime. Tunnelling and Underground Space Technology, 116, 104092.

[23]

Kim, H., Bang, S., Jeong, H., Ham, Y., & Kim, H. (2018). Analyzing context and productivity of tunnel earthmoving processes using imaging and simulation. Automation in Construction, 92, 188-198.

[24]

Lei, M. F., Zhang, Y. B., Deng, E., Ni, Y. Q., Xiao, Y. Z., Zhang, Y., & Zhang, J. J. (2024). Intelligent recognition of joints and fissures in tunnel faces using an improved mask region-based convolutional neural network algorithm. Computer-Aided Civil and Infrastructure Engineering, 39(8), 1123-1142.

[25]

Li, T., Li, X. J., Rui, Y., Ling, J. X., Zhao, S. C., & Zhu, H. H. (2024a). Digital twin for intelligent tunnel construction. Automation in Construction, 158, 105210.

[26]

Li, X. J., Zhao, S. C., Shen, Y., Xue, Y. D., Li, T., & Zhu, H. H. (2024b). Big data-driven TBM tunnel intelligent construction system with automated-compliance-checking (ACC) optimization. Expert Systems with Applications, 244, 122972.

[27]

Liu, D. H., Xuan, P., Li, S., & Huang, P. Z. (2015). Schedule risk analysis for TBM Tunnelling based on adaptive cyclone simulation in a geologic uncertainty-aware context. Journal of Computing in Civil Engineering, 29(6), 04014103.

[28]

Liu, W., Zhao, T. S., Zhou, W., & Tang, J. J. (2018). Safety risk factors of metro tunnel construction in China: An integrated study with EFA and SEM. Safety Science, 105, 98-113.

[29]

Liu, Y., Feng, J., Lu, J. M., & Zhou, S. Y. (2024). A review of digital twin capabilities, technologies, and applications based on the maturity model. Advanced Engineering Informatics, 62, 102592.

[30]

Metropolis, N., & Ulam, S . (1949). The monte carlo method. Journal of the American Statistical Association, 44(247), 335-341.

[31]

Min, S., & Einstein, H. H. (2016). Resource scheduling and planning for tunnelling with a new resource model of the Decision Aids for Tunnelling (DAT). Tunnelling and Underground Space Technology, 51, 212-225.

[32]

Ökmen, Ö., & Öztaş, A. (2008). Construction project network evaluation with correlated schedule risk analysis model. Journal of Construction Engineering and Management, 134(1), 49-63.

[33]

Opoku, D. G. J., Perera, S., Osei-Kyei, R., & Rashidi, M. (2021). Digital twin application in the construction industry: A literature review. Journal of Building Engineering, 40, 102726.

[34]

Persson, F., & Araldi, M. (2009). The development of a dynamic supply chain analysis tool-Integration of SCOR and discrete event simulation. International Journal of Production Economics, 121(2), 574-583.

[35]

Phoon, K. K., Ching, J. Y., & Cao, Z. J. (2022). Unpacking data-centric geotechnics. Underground Space, 7(6), 967-989.

[36]

Phoon, K. K., Pan, Q. J., & Tang, C. (2024). Editorial for machine learning and AI for underground metaverse. Underground Space, 19, 1-3.

[37]

Rabcewicz, L. V. (1964). The new Austrian tunnelling method. Water Power, 17(1), 511-515.

[38]

Rahm, T., Scheffer, M., Thewes, M., König, M., & Duhme, R. (2016). Evaluation of disturbances in mechanized tunnelling using process simulation. Computer-Aided Civil and Infrastructure Engineering, 31(3), 176-192.

[39]

Samaniego, E., Anitescu, C., Goswami, S., Nguyen-Thanh, V. M., Guo, H., Hamdia, K., Zhuang, X., & Rabczuk, T. (2020). An energy approach to the solution of partial differential equations in computational mechanics via machine learning: Concepts, implementation and applications. Computer Methods in Applied Mechanics and Engineering, 362, 112790.

[40]

Schittkowski, K. (2002). EASY-FIT: A software system for data fitting in dynamical systems. Structural and Multidisciplinary Optimization, 23, 153-169.

[41]

Sharma, P. (2015). Discrete-event simulation. International Journal of Scientific & Technology Research, 4(4), 136-140.

[42]

Shen, Y., Ling, J. X., Li, X. J., Li, H. J., Feng, S. Z., & Zhu, H. H. (2022). Holistic digital-twin-based framework to improve tunnel lighting environment: From methodology to application. Building and Environment, 224, 109562.

[43]

Si, S. L., You, X. Y., Liu, H. C., & Zhang, P. (2018). DEMATEL technique: A systematic review of the state-of-the-art literature on methodologies and applications. Mathematical Problems in Engineering, 2018, 3696457.

[44]

Sousa, R. L., & Einstein, H. H. (2012). Risk analysis during tunnel construction using Bayesian Networks: Porto Metro case study. Tunnelling and Underground Space Technology, 27(1), 86-100.

[45]

Sousa, R. L., & Einstein, H. H. (2021). Lessons from accidents during tunnel construction. Tunnelling and Underground Space Technology, 113, 103916.

[46]

Špačková, O., Šejnoha, J., & Straub, D. (2013). Probabilistic assessment of tunnel construction performance based on data. Tunnelling and Underground Space Technology, 37, 62-78.

[47]

Tao, F., Liu, W. R., Zhang, M., Hu, T. L., Qi, Q. L., Zhang, H., Sui, F. Y., Wang, T., Xu, H., Huang, Z. G., Ma, X., Zhang, L. C., Cheng, J. F., Yao, N. K., Yi, W. M., Zhu, K. Z., Zhang, X. S., Meng, F. J., Jin, X. H., Liu, Z. B., He, L. R., Cheng, H., Zhou, E. Z., Li, Y., Lyu, Q., & Luo, Y. M. (2019a). Five-dimension digital twin model and its ten applications. Computer Integrated Manufacturing Systems, 25(1), 1-18 (in Chinese).

[48]

Tao, F., Qi, Q. L., Wang, L. H., & Nee, A. Y. C. (2019b). Digital twins and cyber-physical systems toward smart manufacturing and industry 4.0: Correlation and comparison. Engineering, 5(4), 653-661.

[49]

Einstein, H. H., & Vick, S. G. (1974). Geologic model for a tunnel cost model. In Proceedings of the 2nd North American Rapid Excavation and Tunnelling Conference (pp. 1701-1720).

[50]

Wang, F., Li, H., Li, G., You, Z. J., & Chen, E. J. (2024a). Characterization of geological uncertainties from limited boreholes using copula-based coupled Markov chains for underground construction. Underground Space, 16, 94-105.

[51]

Wang, J. X., Li, P. N., Zhuang, X. Y., Li, X. J., Jiang, X., & Wu, J. (2024b). Multi-source data integration and multi-scale modeling framework for progressive prediction of complex geological interfaces in Tunnelling. Underground Space, 15, 1-25.

[52]

Wang, X. R. (2020). Uncertainty quantification and reduction in the characterization of subsurface stratigraphy using limited geotechnical investigation data. Underground Space, 5(2), 125-143.

[53]

Wang, X. R., Li, Z., Wang, H., Rong, Q. G., & Liang, R. Y. (2016). Probabilistic analysis of shield-driven tunnel in multiple strata considering stratigraphic uncertainty. Structural Safety, 62, 88-100.

[54]

Wang, X. R., Wang, H., & Liang, R. Y. (2018). A method for slope stability analysis considering subsurface stratigraphic uncertainty. Landslides, 15, 925-936.

[55]

Wellmann, J. F., & Regenauer-Lieb, K. (2012). Uncertainties have a meaning: Information entropy as a quality measure for 3-D geological models. Tectonophysics, 526-529, 207-216.

[56]

Wu, F. Y. (1982). The potts model. Reviews of Modern Physics, 54(1), 235-268.

[57]

Xiao, H. H., Yang, W. K., Hu, J., Zhang, Y. P., Jing, L. J., & Chen, Z. Y. (2022). Significance and methodology: Preprocessing the big data for machine learning on TBM performance. Underground Space, 7(4), 680-701.

[58]

Ye, Z. J., Ye, Y., Zhang, C. P., Zhang, Z. M., Li, W., Wang, X. J., Wang, L., & Wang, L. B. (2023). A digital twin approach for tunnel construction safety early warning and management. Computers in Industry, 144, 103783.

[59]

Yu, G., Lin, D. H., Wang, Y., Hu, M., Sugumaran, V., & Chen, J. J. (2023). Digital Twin-enabled and Knowledge-driven decision support for tunnel electromechanical equipment maintenance. Tunnelling and Underground Space Technology, 140, 105318.

[60]

Yu, J., Zhong, D. H., Ren, B. Y., Tong, D. W., & Hong, K. (2017). Probabilistic risk analysis of diversion tunnel construction simulation. Computer-Aided Civil and Infrastructure Engineering, 32(9), 748-771.

[61]

Zhu, H. H., Li, X. J., & Lin, X. D. (2018). Infrastructure smart service system (iS3) and its application. China Civil Engineering Journal, 51(1), 1-12 (in Chinese).

PDF (9479KB)

11

Accesses

0

Citation

Detail

Sections