Risk reduction in a project portfolio

Dujuan Guan , Peng Guo , Keith W. Hipel , Liping Fang

Journal of Systems Science and Systems Engineering ›› 2017, Vol. 26 ›› Issue (1) : 3 -22.

PDF
Journal of Systems Science and Systems Engineering ›› 2017, Vol. 26 ›› Issue (1) : 3 -22. DOI: 10.1007/s11518-016-5296-2
Article

Risk reduction in a project portfolio

Author information +
History +
PDF

Abstract

The positive impacts of managing projects as a portfolio are quantified by comparing the value of the integrated risk of a project portfolio and the aggregation of single project risks implemented separately. Firstly, the integrated risk is defined by proposing risky events based on set theory. Secondly, as projects interact with each other in a project portfolio, the integrated risk is evaluated by using a Bayesian network structure learning algorithm to construct an interdependent network of risks. Finally, the integrated risk of a practical case is assessed using this method, and the results show that the proposed method is an effective tool for calculating the extent of risk reduction of implementing a project portfolio and identifying the most risky project, so as to assist companies in making comprehensive decisions in the phase of portfolio selection and portfolio controlling.

Keywords

Project portfolio / integrated risk / set theory / Bayesian network / risk assessment

Cite this article

Download citation ▾
Dujuan Guan, Peng Guo, Keith W. Hipel, Liping Fang. Risk reduction in a project portfolio. Journal of Systems Science and Systems Engineering, 2017, 26(1): 3-22 DOI:10.1007/s11518-016-5296-2

登录浏览全文

4963

注册一个新账户 忘记密码

References

[1]

Baker N., Freeland J.. Recent advances in R&D benefit measurement and project selection methods. Management Science, 1975, 21(10): 1164-1175.

[2]

Beringer C., Jonas D., Gemünden H.N.. Establishing project portfolio management: an exploratory analysis of the influence of internal stakeholders’ interactions. Project Management Journal, 2012, 43(6): 17-32.

[3]

Beringer C., Jonas D., Kock A.. Behavior of internal stakeholders in project portfolio management and its impact on success. International Journal of Project Management, 2013, 31(6): 830-846.

[4]

Bhattacharyya R., Kumar P., Kar S.. Fuzzy R&D portfolio selection of interdependent projects. Computers and Mathematics with Applications, 2011, 62(10): 3857-3870.

[5]

Campos L.M.. A scoring function for learning Bayesian networks based on mutual information and conditional independence tests. The Journal of Machine Learning Research, 2006, 7: 2149-2187.

[6]

Chen X.W., Anantha G., Lin X.. Improving Bayesian network structure learning with mutual information-based node ordering in the K2 algorithm. IEEE Transactions on Knowledge and Data Engineering, 2008, 20(5): 628-640.

[7]

Cooper G.F., Herskovits E.. A Bayesian method for the induction of probabilistic networks from data. Machine Learning, 1992, 9(4): 309-347.

[8]

Costa H.R., de O Barros M., Travassos G.H.. A risk based economical approach for evaluating software project portfolios. In ACM SIGSOFT Software Engineering Notes, 2005, 30(4): 1-5.

[9]

Cover T.M., Thomas J.A.. Elements of Information Theory, 2012, Hoboken, N.J.: Wiley.

[10]

Dickinson M.W., Thornton A.C., Graves S.. Technology portfolio management: optimizing interdependent projects over multiple time periods. IEEE Transactions on Engineering Management, 2001, 48(4): 518-527.

[11]

Eilat H., Golany P.B., Shtub A.. Constructing and evaluating balanced portfolios of R&D projects with interactions: a DEA based methodology. European Journal of Operational Research, 2006, 172(3): 1018-1039.

[12]

Gallati R.. Risk Management and Capital Adequacy, 2003, New York: McGraw Hill Professional

[13]

Ghapanchi A.H., Tavana M., Khakbaz M.H., Low G.. A methodology for selecting portfolios of projects with interactions and under uncertainty. International Journal of Project Management, 2012, 30(7): 791-803.

[14]

Guan D.J., Guo P.. Relationship classification of project portfolio based on the measurement of interaction effects and their influences. Soft Science, 2014, 28(10): 125-129.

[15]

Guan D.J., Hipel K.W., Fang L., Guo P.. Assessing project portfolio risk based on Bayesian network. IEEE International Conference on Systems, Man, and Cybernetics: 1546-1551, 2014

[16]

Guo N., Yu S.. Risk and uncertainty in project portfolio management. International Conference on Information Engineering and Applications, 2013, 3: 815-822.

[17]

Heckerman D., Geiger D., Chickering D.M.. Learning Bayesian networks: the combination of knowledge and statistical data. Machine Learning, 1995, 20(3): 197-243.

[18]

Jaafari A.. Management of risks, uncertainties and opportunities on projects: time for a fundamental shift. International Journal of Project Management, 2001, 19(2): 89-101.

[19]

Jensen F.V.. An Introduction to Bayesian Networks, 1996, London: UCL Press

[20]

Ji J., Hu R., Zhang H., Liu C.. A hybrid method for learning Bayesian networks based on ant colony optimization. Applied Soft Computing, 2011, 11(4): 3373-3384.

[21]

Jonas D.. Empowering project portfolio managers: how management involvement impacts project portfolio management performance. International Journal of Project Management, 2010, 28(8): 818-831.

[22]

Kiiveri H., Speed T.P., Carlin J.B.. Recursive causal models. Journal of the Australian Mathematical Society, 1984, 36(1): 30-52.

[23]

Kolmogorov A.. Logical basis for information theory and probability theory. IEEE Transactions on Information Theory, 1968, 14(5): 662-664.

[24]

Markowitz H.. Portfolio selection. The Journal of Finance, 1952, 7(1): 77-91.

[25]

Martinsuo M.. Project portfolio management in practice and in context. International Journal of Project Management, 2013, 31(6): 794-803.

[26]

Martinsuo M., Lehtonen P.. Role of single-project management in achieving portfolio management efficiency. International Journal of Project Management, 2007, 25(1): 56-65.

[27]

Marwell G., Oliver P.E., Prahl R.. Social networks and collective action: a theory of the critical mass, III. American Journal of Sociology, 1988, 94(3): 502-534.

[28]

McFarlan F.W.. Portfolio approach to information systems. Harvard Business Review, 1981, 59(5): 142-150.

[29]

Nielsen T.D., Jensen F.V.. Bayesian Networks and Decision Graphs, 2009, New York: Springer.

[30]

Olsson R.. Risk management in a multi-project environment: an approach to manage portfolio risks. International Journal of Quality & Reliability Management, 2008, 25(1): 60-71.

[31]

Pearl J.. Probabilistic Reasoning in Intelligent Systems: Networks of Plausible Inference, 1988.

[32]

Pennypacker J.S., Dye L.D.. Project portfolio management and managing multiple projects: two sides of the same coin. Project Management Institute Annual Seminars & Symposium: 1-10, Houston, 2002

[33]

Petit Y.. Project portfolios in dynamic environments: organizing for uncertainty. International Journal of Project Management, 2012, 30(5): 539-553.

[34]

PMI Project Management Institute A Guide to the Project Management Body of Knowledge, 2008

[35]

Proakis J.G.. Digital Communications, 1995.

[36]

Sanchez H., Robert B., Pellerin R.. A project portfolio risk-opportunity identification framework. Project Management Journal, 2008, 39(3): 97-109.

[37]

Schmidt R.L.. A model for R&D project selection with combined benefit, outcome and resource interactions. IEEE Transactions on Engineering Management, 1993, 40(4): 403-410.

[38]

Shannon C.E., Weaver W.. A mathematical theory of communication. Bell System Technical Journal, 1948, 27(10): 623-656.

[39]

Stamelos I., Angelis L., Dimou P., Sakellaris E.. On the use of Bayesian belief networks for the prediction of software productivity. Information and Software Technology, 2003, 45(1): 51-60.

[40]

Teller J.. Portfolio risk management and its contribution to project portfolio success: an investigation of organization, process, and culture. Project Management Journal., 2013, 44(2): 36-51.

[41]

Wang M., Chen Z., Cloutier S.. A hybrid Bayesian network learning method for constructing gene networks. Computational Biology and Chemistry, 2007, 31(5): 361-372.

[42]

Wang S.Y.. The development of microelectronics technology: the concept of “critical mass” and reform competition. China High Technology Enterprises, 1997, 1: 5-9.

[43]

Zhao J., Guo P., Pan N.Z.. Risk measurement and selection optimization of project portfolio based on the interaction effect. Operations Research and Management Science, 2011, 20(6): 120-126.