Effect of cantilever soldier pile foundation excavation closing to an existing composite foundation

Gui-he Wang , Yu-you Yang

Journal of Central South University ›› 2013, Vol. 20 ›› Issue (5) : 1384 -1396.

PDF
Journal of Central South University ›› 2013, Vol. 20 ›› Issue (5) : 1384 -1396. DOI: 10.1007/s11771-013-1626-4
Article

Effect of cantilever soldier pile foundation excavation closing to an existing composite foundation

Author information +
History +
PDF

Abstract

Adjacent high-rise building with CFG pile composite foundation was studied using model test method to investigate stress and displacement of the foundation pile retaining structure, the subsidence and transmogrification law of the composite foundation. Two different project cases with and without high-rise building adjacent to pile foundation were compared. The relationships of slope pile bending moment, earth pressure, pile top displacement and complex settlement with respect to time were obtained. 1) When there is no adjacent building, the displacement of supporting system caused by excavation is mainly in the horizontal direction; while when the adjacent building exists, the displacement of supporting system will be vertical. 2) When the excavation depth is less than or equal to the adjacent building’s composite foundation depth, the force of supporting structure is uniform and has small value, at the same time, the pile strength is in fully use and the foundation is stable; while when the excavation depth is greater than the depth of adjacent building’s composite foundation, the results will be opposite. 3) During the excavation process, the adjustment of the composite ground loads on the supporting structure is carried out downward and the force of the supporting structure is reduced through the deformation of the bearing layer.

Keywords

model test / foundation / adjacent high-rise building / composite foundation

Cite this article

Download citation ▾
Gui-he Wang, Yu-you Yang. Effect of cantilever soldier pile foundation excavation closing to an existing composite foundation. Journal of Central South University, 2013, 20(5): 1384-1396 DOI:10.1007/s11771-013-1626-4

登录浏览全文

4963

注册一个新账户 忘记密码

References

[1]

ShangY-l, LiQ, YangT-feng, et al. HENGW, et al. . Application of CFG piles for soft foundation treatment in the Wuhan-Guangzhou railway passenger special line [C]. ICCTP 2010: Integrated Transportation System-Green, Intelligent, Reliable, 2010BeijingASCE3382-3390

[2]

ZhengJ-j, AbushararS W, WangX-zhi. Three-dimensional nonlinear finite element modeling of composite foundation formed by CFG-lime piles [J]. Computers and Geotechnics, 2008, 35(4): 637-643

[3]

LiuZ, ZhuJ-g, ZhangZ-liang. Dynamic response analysis of composition foundation with CFG piles [J]. Advanced Materials Research, 2012, 368/373: 201-205

[4]

XiangJian. Dynamic response analysis on efficacy of CFG-pile in different height [J]. Advanced Materials Research, 2011, 311/312/313: 145-148

[5]

ChenQ-n, ZhaoM-h, ZhouG-hua. Bearing capacity and mechanical behavior of CFG pile composite foundation [J]. Journal of Central South University of Technology, 2008, 15(Supp.2): 45-49

[6]

LinQ-x, LiS-h, ZhouL-qiangHUJ. CFG pile composite foundation failure mode of the finite element analysis of the influence factors [C]. 2012 2nd International Conference on Applied Social Science (ICASS 2012), 2012Newark, USAInformation Engineering Research Inst215-219

[7]

MaP, QinS-q, QianH-tao. Calculation of active earth pressure for limited soils [J]. Chinese Journal of Rock Mechanics and Engineering, 2008, 27(Supp.1): 3070-3074

[8]

GaoY-li. Calculation of finite earth pressure with limit analysis method [J]. Building Structures, 2001, 31(8): 66-68

[9]

YingH-q, GePeng. Value engineering research and design optimization in small-scale excavation project [J]. Chinese Journal of Underground Space and Engineering, 2006, 2(1): 166-169

[10]

WangJ, ZhouJ, XuJ-ye. Research on settlement control of CFG pile-cap-net structure subgrade based on field test of high-speed railway [J]. Railway Investigation and Surveying, 2012, 38(4): 17-21

[11]

WenS-congOptimization design study based on the settlement control of high-speed railway CFG pile composite foundation [D], 2012BeijingBeijing Jiaotong University

[12]

LiQ-m, WangS-r, TangY-q, HeM-chao. Experimental research on squeezed pan piles in double-row as retaining and protecting of foundation excavation [J]. Rock and Soil Mechanics, 2009, 30(5): 1328-1332

[13]

ZhangJ-h, ZhangY, PuJ-l, WeiZ-x, GaoY-li. Centrifuge modeling of soil nail reinforcements [J]. China Civil Engineering Journal, 2009, 42(1): 76-80

[14]

FrydmanS, BakerR, LevyA. Modeling the soil nailing excavation process [C]. Centrifuge 94, 1994RotterdamNetherlands669-674

[15]

WangH-d, DengJ-p, LuoJie. Nondestructive monitoring experiments on length of CFG piles by GPR [J]. Applied Mechanics and Materials, 2011, 90/91/92/93: 298-301

[16]

YuanJ-y, LiZ-juan. Dynamic numerical analysis on efficacy of CFG-PILE caps in low embankment [C]. Proceedings of the Eleventh International Symposium on Structural Engineering, 2010BeijingScience Press Beijing935-939

AI Summary AI Mindmap
PDF

109

Accesses

0

Citation

Detail

Sections
Recommended

AI思维导图

/