A three-stage method with efficient calculation for lot streaming flow-shop scheduling

Hai-yan WANG, Fu ZHAO, Hui-min GAO, John W. SUTHERLAND

PDF(824 KB)
PDF(824 KB)
Front. Inform. Technol. Electron. Eng ›› 2019, Vol. 20 ›› Issue (7) : 1002-1020. DOI: 10.1631/FITEE.1700457
Orginal Article
Orginal Article

A three-stage method with efficient calculation for lot streaming flow-shop scheduling

Author information +
History +

Abstract

An important production planning problem is how to best schedule jobs (or lots) when each job consists of a large number of identical parts. This problem is often approached by breaking each job/lot into sublots (termed lot streaming). When the total number of transfer sublots in lot streaming is large, the computational effort to calculate job completion time can be significant. However, researchers have largely neglected this computation time issue. To provide a practical method for production scheduling for this situation, we propose a method to address the n-job, m-machine, and lot streaming flow-shop scheduling problem. We consider the variable sublot sizes, setup time, and the possibility that transfer sublot sizes may be bounded because of capacity constrained transportation activities. The proposed method has three stages: initial lot splitting, job sequencing optimization with efficient calculation of the makespan/total flow time criterion, and transfer adjustment. Computational experiments are conducted to confirm the effectiveness of the three-stage method. The experiments reveal that relative to results reported on lot streaming problems for five standard datasets, the proposed method saves substantial computation time and provides better solutions, especially for large-size problems.

Keywords

Lot streaming / Flow-shop scheduling / Transfer sublots / Variable size / Bounded size / Differential evolution

Cite this article

Download citation ▾
Hai-yan WANG, Fu ZHAO, Hui-min GAO, John W. SUTHERLAND. A three-stage method with efficient calculation for lot streaming flow-shop scheduling. Front. Inform. Technol. Electron. Eng, 2019, 20(7): 1002‒1020 https://doi.org/10.1631/FITEE.1700457

RIGHTS & PERMISSIONS

2019 Zhejiang University and Springer-Verlag GmbH Germany, part of Springer Nature
PDF(824 KB)

Accesses

Citations

Detail

Sections
Recommended

/