Last Planner System and Scrum: Comparative analysis and suggestions for adjustments

Roshan POUDEL, Borja GARCIA de SOTO, Eder MARTINEZ

PDF(677 KB)
PDF(677 KB)
Front. Eng ›› 2020, Vol. 7 ›› Issue (3) : 359-372. DOI: 10.1007/s42524-020-0117-1
RESEARCH ARTICLE
RESEARCH ARTICLE

Last Planner System and Scrum: Comparative analysis and suggestions for adjustments

Author information +
History +

Abstract

This study provides a critical review of the concepts of Agile, Lean, Scrum, and Last Planner® System (LPS). A comparative analysis is conducted between LPS and Scrum to expand LPS by considering Scrum’s best practices. Eight dimensions, namely, 1) origins, 2) main purpose, 3) overall system/framework process, 4) tools or artifacts maintained by the team, 5) team composition and main roles, 6) regular events or team meetings, 7) metrics/dashboards, and 8) approach to learning, are evaluated. After analyzing side by side the eight dimensions, it was found that many aspects from Scrum already exist in LPS in the same or similar form. However, the authors identify four main elements from Scrum that can be leveraged to improve the LPS benchmark, such as considering the Scrum “Increment” concept into LPS, having a clear definition of roles and responsibilities, or adding an equivalent to a Scrum Master to have a designated “rule keeper” in LPS. These opportunities to be considered in new LPS benchmarks need to be tested and validated with real applications. To the best of the authors’ knowledge, this work is the first to comprehensively compare Scrum (Agile) and LPS (Lean) and could be seen as a contribution toward the evolution of the Last Planner System for the academic and industrial environments.

Keywords

Lean Construction / Last Planner System / Agile / Scrum / comparative analysis / AEC projects / project teams

Cite this article

Download citation ▾
Roshan POUDEL, Borja GARCIA de SOTO, Eder MARTINEZ. Last Planner System and Scrum: Comparative analysis and suggestions for adjustments. Front. Eng, 2020, 7(3): 359‒372 https://doi.org/10.1007/s42524-020-0117-1

References

[1]
Abbas N, Gravell A M, Wills G B (2008). Historical roots of Agile methods: Where did “Agile thinking” come from? In: International Conference on Agile Processes and Extreme Programming in Software Engineering. Berlin, Heidelberg: Springer, 94–103
[2]
AIA (2007). Integrated Project Delivery: A Guide. Version 1. The American Institute of Architects (AIA)
[3]
Ballard G (2000). The Last Planner System of Production Control. Dissertation for the Doctoral Degree. Birmingham: University of Birmingham
[4]
Ballard G, Hammond J, Nickerson R (2009). Production control principles. In: Proceedings of the 17th Annual Conference of the International Group for Lean Construction (IGLC). Taipei, 489–500
[5]
Ballard G, Howell G (1998). Shielding production: Essential step in production control. Journal of Construction Engineering and Management, 124(1): 11–17
CrossRef Google scholar
[6]
Ballard G, Howell G, Casten M (1996). PARC: A case study. In: Proceedings of the 4th Annual Conference of the International Group for Lean Construction (IGLC). Birmingham
[7]
Ballard G, Howell G A (2003a). Competing construction management paradigms. In: Construction Research Congress: Wind of Change —Integration and Innovation, 1–8
[8]
Ballard G, Howell G A (2003b). An update on last planner. In: Proceedings of the 11th Annual Conference of the International Group for Lean Construction (IGLC). Blacksburg, VA
[9]
Ballard G, Tommelein I D (2016). Current process benchmark for the last planner system. Lean Construction Journal, 89: 57–89
[10]
Barlow J (1998). From craft production to mass customisation? Customer-focused approaches to housebuilding. In: Proceedings of the 6th Annual Conference of the International Group for Lean Construction (IGLC). Sao Paulo
[11]
Beck K, Beedle M, van Bennekum A, Cockburn A, Cunningham W, Fowler M, Grenning J, Highsmith J, Hunt A, Jeffries R, Kern J, Marick B, Martin R C, Mellor S, Schwaber K, Sutherland J, Thomas D (2001). Manifesto for Agile Software Development
[12]
Boyes H A (2013). Cyber security of intelligent buildings: A review. In: 8th IET International System Safety Conference incorporating the Cyber Security Conference. Cardiff
[13]
Caballero E, Calvo-Manzano J A, San Feliu T (2011). Introducing scrum in a very small enterprise: A productivity and quality analysis. In: O‘Connor R V, Pries-Heje J, Messnarz R, eds. European Conference on Software Process Improvement. Systems, Software and Service Process Improvement. Roskilde: Springer, 215–224
[14]
Cardozo E S F, Araújo Neto J B F, Barza A, França A C C, da Silva F Q B (2010). SCRUM and productivity in software projects: A systematic literature review. In: 14th International Conference on Evaluation and Assessment in Software Engineering (EASE). Keele University, 1–4
[15]
Cervone H F (2011). Understanding Agile project management methods using Scrum. OCLC Systems & Services: International Digital Library Perspectives, 27(1): 18–22
[16]
Ciric D, Lalic B, Gracanin D, Palcic I, Zivlak N (2018). Agile project management in new product development and innovation processes: Challenges and benefits beyond software domain. In: 2018 International Symposium on Innovation and Entrepreneurship (TEMS-ISIE). Beijing, 1–9
[17]
Cohn M (2005). Agile Estimating and Planning. Englewood: Prentice Hall
[18]
Cohn M (2014). My primary criticism of scrum. Available at: mountaingoatsoftware.com/blog
[19]
Dave B, Boddy S, Koskela L (2011). VisiLean: Designing a production management system with lean and BIM. In: Proceedings of the 19th Annual Conference of the International Group for Lean Construction (IGLC). Lima, 477–487
[20]
Dave B, Boddy S, Koskela L (2013). Challenges and opportunities in implementing lean and BIM on an infrastructure project. In: Proceedings of the 21st Annual Conference of the International Group for Lean Construction (IGLC). Fortaleza, 741–750
[21]
Dave B, Hämäläinen J P, Koskela L (2015). Exploring the recurrent problems in the last planner implementation on construction projects. In: Proceedings of the Indian Lean Construction Conference (ILCC 2015). Institute for Lean Construction Excellence
[22]
Demir S T, Theis P (2016). Agile design management—The application of Scrum in the design phase of construction projects. In: Proceedings of the 24th Annual Conference of the International Group for Lean Construction. Boston, MA, 13–22
[23]
El Samad G, Hamzeh F R, Emdanat S (2017). Last planner system—The need for new metrics. In: Proceedings of the 25th Annual Conference of the International Group for Lean Construction (IGLC). Heraklion, 637–644
[24]
Fischer M, Ashcraft H W, Reed D, Khanzode A (2017). Integrating Project Delivery. Hoboken: John Wiley & Sons
[25]
Fisk D (2012). Cyber security, building automation, and the intelligent building. Intelligent Buildings International, 4(3): 169–181
CrossRef Google scholar
[26]
García de Soto B, Adey B T, Fernando D (2017). A hybrid methodology to estimate construction material quantities at an early project phase. International Journal of Construction Management, 17(3): 165–196
CrossRef Google scholar
[27]
García de Soto B, Agustí-Juan I, Joss S, Hunhevicz J (2019). Implications of construction 4.0 to the workforce and organizational structures. International Journal of Construction Management, 1–13
[28]
Gonzalez V, Alarcon L F, Mundaca F (2008). Investigating the relationship between planning reliability and project performance. Production Planning and Control, 19(5): 461–474
CrossRef Google scholar
[29]
Grenning J (2002). Planning poker or how to avoid analysis paralysis while release planning. Hawthorn Woods: Renaissance Software Consulting, 3: 22–23
[30]
Hajdu M (2018). Survey of precedence relationships: Classification and algorithms. Automation in Construction, 95: 245–259
CrossRef Google scholar
[31]
Hajdu M, Lucko G, Su Y (2017). Singularity functions for continuous precedence relations and nonlinear activity-time-production functions. Automation in Construction, 79: 31–38
CrossRef Google scholar
[32]
Hamdi O, Leite F (2012). BIM and Lean interactions from the BIM capability maturity model perspective: A case study. In: Proceedings of the 20th Annual Conference of the International Group for Lean Construction (IGLC). San Diego, CA
[33]
Hamzeh F R, Aridi O Z (2013). Modeling the last planner system metrics: A case study of an AEC company. In: Proceedings of the 21st Annual Conference of the International Group for Lean Construction (IGLC). Fortaleza, 599–608
[34]
Hamzeh F R, Ballard G, Tommelein I D (2009). Is the Last Planner System applicable to design? A case study. In: Proceedings of the 17th Annual Conference of the International Group for Lean Construction (IGLC). Taipei, 165–176
[35]
Heigermoser D, García de Soto B, Abbott E L S, Chua D K H (2019). BIM-based Last Planner System tool for improving construction project management. Automation in Construction, 104: 246–254
CrossRef Google scholar
[36]
Highsmith J, Cockburn A (2001). Agile software development: The business of innovation. Computer, 34(9): 120–127
CrossRef Google scholar
[37]
Hossain E, Babar M A, Paik H Y (2009). Using scrum in global software development: A systematic literature review. In: 4th IEEE International Conference on Global Software Engineering. Limerick, 175–184
[38]
Iamandi O, Popescu S, Dragomir M, Morariu C (2015). A critical analysis of project management models and its potential risks in software development. Calitatea, 16(149): 55–61
[39]
Kalsaas B T, Bonnier K E, Ose A O (2016). Towards a model for planning and controlling ETO design projects. In: Proceedings of the 24th Annual Conference of the International Group for Lean Construction (IGLC). Boston, MA, 33–42
[40]
Khan S, Tzortzopoulos P (2015). Improving design workflow with the last planner system: Two action research studies. In: Proceedings of the 23rd Annual Conference of the International Group for Lean Construction (IGLC). Perth, 568–577
[41]
Koskela L (1992). Application of the new production philosophy to construction. CIFE Technical Report #72. Stanford: Stanford University
[42]
Koskela L (2000). An Exploration towards a Production Theory and Its Application to Construction. Dissertation for the Doctoral Degree. Espoo: VTT Technical Research Centre of Finland
[43]
Koskela L, Ballard G, TanhuanpääV P (1997). Towards lean design management. In: Proceedings of the 5th Annual Conference of the International Group for Lean Construction (IGLC). Gold Coast, 1–13
[44]
Koskela L, Howell G (2002). The theory of project management: Explanation to novel methods. In: Proceedings of the 10th Annual Conference of the International Group for Lean Construction (IGLC). Gramado, 1–11
[45]
Krafcik J F (1988). Triumph of the Lean production system. MIT Sloan Management Review, 30(1): 41
[46]
Kupp M, Dahlander L, Morrow E (2015). Team Wikispeed: Developing hardware the software way. Case Study. European School of Management and Technology
[47]
Larman C, Vodde B (2010). Practices for Scaling Lean & Agile Development: Large Multisite and Offshore Product Development with Large-Scale Scrum. Upper Saddle River, NJ: Addison-Wesley Professional
[48]
Lessing J, Stehn L, Ekholm A (2005). Industrialised housing: Definition and categorization of the concept. In: Proceedings of the 13th Annual Conference of the International Group for Lean Construction (IGLC). Sydney, 471–480
[49]
Lia K A, Ringerike H, Kalsaas B T (2014). Increase predictability in complex engineering and fabrication projects. In: Proceedings of the 22nd Annual Conference of the International Group for Lean Construction (IGLC). Oslo, 437–449
[50]
Liu M, Ballard G (2008). Improving labor productivity through production control. In: Proceedings of the 16th Annual Conference of the International Group for Lean Construction (IGLC). Manchester, 657–666
[51]
Liu M, Ballard G, Ibbs W (2011). Work flow variation and labor productivity: Case study. Journal of Management Engineering, 27(4): 236–242
CrossRef Google scholar
[52]
Lu W, Olofsson T, Jensen P, Simonsson P (2011). BIM-based lean-agile supply chain for industrialized housing. In: International Conference on Construction Applications of Virtual Reality. Bauhaus-Universität Weimar, 262–270
[53]
Mantha B, García de Soto B (2019). Cyber security challenges and vulnerability assessment in the construction industry. In: Proceedings of the 2019 Creative Construction Conference. Budapest, 29–37
[54]
Mostafa S, Chileshe N, Abdelhamid T (2016). Lean and agile integration within offsite construction using discrete event simulation: A systematic literature review. Construction Innovation, 16(4): 483–525
CrossRef Google scholar
[55]
Naim M, Naylor J, Barlow J (1999). Developing lean and agile supply chains in the UK housebuilding industry. In: Proceedings of the 7th Annual Conference of the International Group for Lean Construction (IGLC). University of California, Berkeley, CA, 159–170
[56]
Ormeño Zender Y, García de Soto B (2020). Use of Scrum in the rehabilitation of a commercial building in Peru. Construction Innovation: Information, Process, Management. In press,
CrossRef Google scholar
[57]
Oskouie P, Gerber D J, Alves T, Becerik-Gerber B (2012). Extending the interaction of building information modeling and lean construction. In: Proceedings of the 20th Annual Conference of the International Group for Lean Construction (IGLC). San Diego, CA, 111–120
[58]
Owen R L, Koskela L (2006). Agile construction project management. In: 6th International Postgraduate Research Conference in the Built and Human Environment, 6(7): 22–33
[59]
Owen R L, Koskela L J, Henrich G, Codinhoto R (2006). Is Agile project management applicable to construction? In: Proceedings of the 14th Annual Conference of the International Group for Lean Construction (IGLC). Pontificia Universidad Católica de Chile, Santiago, 51–66
[60]
Paasivaara M, Lassenius C (2011). Scaling Scrum in a large distributed project. In: International Symposium on Empirical Software Engineering and Measurement. Banff, 363–367
[61]
Paasivaara M, Lassenius C (2016). Scaling scrum in a large globally distributed organization: A case study. In: IEEE 11th International Conference on Global Software Engineering (ICGSE). Irvine, CA, 74–83
[62]
Parn E A, Edwards D (2019). Cyber threats confronting the digital built environment: Common data environment vulnerabilities and block chain deterrence. Engineering, Construction, and Architectural Management, 26(2): 245–266
CrossRef Google scholar
[63]
Royce W W (1970). Managing the development of large software systems. In: Proceedings of the 9th International Conference on Software Engineering. IEEE WESCON, 328–338
[64]
Rubin K S (2012). Essential Scrum: A Practical Guide to the Most Popular Agile Process. Upper Saddle River, NJ: Addison-Wesley
[65]
Sacks R, Barak R, Belaciano B, Gurevich U, Pikas E (2013). KanBIM workflow management system: Prototype implementation and field testing. Lean Construction Journal, 19–35
[66]
Sacks R, Koskela L, Dave B, Owen R (2010). Interaction of lean and building information modeling in construction. Journal of Construction Engineering and Management, 136(9): 968–980
CrossRef Google scholar
[67]
Sanchez L M, Nagi R (2001). A review of Agile manufacturing systems. International Journal of Production Research, 39(16): 3561–3600
CrossRef Google scholar
[68]
Sanvido V E, Konchar M (1999). Selecting project delivery systems: Comparing design-build, design-bid-build and construction management at risk. Project Delivery Institute, State College, PA
[69]
Schwaber K (2007). The Enterprise and Scrum. Redmond, WA: Microsoft Press
[70]
Schwaber K, Beedle M (2001). Agile Software Development with Scrum. Upper Saddle River, NJ: Prentice Hall
[71]
Schwaber K, Sutherland J (2013). The Scrum GuideTM: The definitive guide to Scrum—The rules of the game
[72]
Sriprasert E, Dawood N (2003). Multi-constraint information management and visualization for collaborative planning and control in construction. Journal of Information Technology in Construction, 8: 341–366
[73]
Streule T, Miserini N, Bartlomé O, Klippel M, García de Soto B (2016). Implementation of scrum in the construction industry. Procedia Engineering, 164: 269–276
CrossRef Google scholar
[74]
Sutherland J, Schwaber K (2007). The Scrum Papers: Nuts, Bolts and Origins of an Agile Process. Cambridge: Scrum Inc.
[75]
Takeuchi H, Nonaka I (1986). The new product development game. Harvard Business Review, 64(1): 137–146
[76]
Tiwari S, Sarathy P (2012). Pull planning as a mechanism to deliver constructible design . In: Proceedings of the 20th Annual Conference of the International Group for Lean Construction (IGLC). San Diego, CA, 18–20
[77]
Tommelein I D, Ballard G (1997). Look-ahead planning: Screening and pulling. Technical Report No. 97-9. Construction Engineering and Management Program, Civil and Environmental Engineering Department, University of California, Berkeley, CA
[78]
Womack J P, Jones D T, Roos D (1990). The Machine that Changed the World: The Story of Lean Production. New York: Rawson Associates